|
|
Give Back
Fundraiser
Renovation Work Completed
1999
- Dining Room
New chairs and dishes were installed into
the Bob Palin Memorial Dining Room thanks to efforts of Bill
Todd '57, Don Oliver '58, Jim Lee '59 and Ron
Lundquist '57. Tables received new oak trimmed tops and light
fixtures were overhauled
2000
- Brick & Mortar All
crumbling mortar on The House was ground out and the bricks repointed
with matching mortar. The front porch step walls were disassembled and
reconstructed. The settled granite steps were fork-lifted back into level
position. Yet to do is the back wall, garage and Ski Shack repair.
-
Entry Tile Floor The badly cracked
and settled tile entry floor was totally removed, the fill compacted,
a 2" slab poured with reinforcing steel mesh and factory ordered
custom 1" square tiles reset in the original pattern by a local
artisan. Both the Brick & Mortar and Entry Tile Floor repairs were
made possible by a generous gift by Jim Murphy ‘51 in memory of
his mother (also Beta Delta’s last House Mother).
-
Galley Doors The weathered USS
Montana Galley Doors featuring the Seals of Montana and US were refinished
and rehung in their place of honor thanks to the efforts of John
Rimel ‘79.
-
Carport Roof Repairs
A team of actives and alumni lead Dan Cederberg ‘75 and Bob Rowe ‘80 carefully
removed the tiles, stacked them on pallets and stored them in the
garage. Damaged wood was repaired with clear redwood and 90 lb.
rolled roofing installed to protect it until the tile roof can be
restored.
-
Sigma Chi Bell Display
At Homecoming
2000, the Sigma Chi Bell was installed in the Adams Field House Lobby
amongst much pomp and ceremony. UM President George Dennison graciously
accepted the loan of the Sigma Bell on behalf of the community as an
enduring symbol of Montana history. Col. Sam Roberts ‘41 gave a
moving speech reminding all of the great sacrifice made by the Beta
Delta War Dead to which the Bell is dedicated. The Bell hangs proudly
atop a cylindrical oak platform capped with a polished granite base
engraved with IN HOC SIGNO VINCES and the White Cross of Sigma Chi. An audio
feature is being added to hear the Bell toll, Beta Delta’s history and
to play "The Sweetheart of Sigma Chi".
2001
Winter Projects
-
Coordinated
by Brad Colberg '82, Bob Rowe '80 and Mark Peterson '76:
-
Boiler Room Firewall Fire walls and doors were installed to
enclose the boiler
-
Basement Stairs Rebuilt The steps leading to the old Pool
Room, now the TV Room, were totally rebuilt.
-
Pool Table Renovation After many years of disrepair, the
pool table was stripped, refinished and new pockets, felt and bumpers
were installed
-
Fire Escape Stair Repair New non-skid treads were added as
well as new handrails to the concrete steps leading to the parking lot.
Summer Projects
-
Roofing
We embarked on our biggest
project with the tile roof. Due to the cost and
availability of the original tile from
Ludowici, it was decided to use Ludowici trim tiles (hip and ridge
only) and supplement them with
Gladding McBean field tiles. Gladding McBean tiles carry a 75
year warranty (same as Ludowici) and are 75% less expensive.
Included in the roofing project is the garage which hasn't had a tile
roof for 30 years. In the early 1970s, the tile was removed to
repair the House roof.
The roof repair proved to be daunting. Sections of
the fire escape had to be removed as well as all the tile and
underlayment. Dryrot repair was done in selected areas as well as
considerable wasp control (lots of nice tile voids for nesting).
All of the fascia was replaced with high quality redwood. When the
roof deck was all repaired, the entire roof was covered with ice and
water shield underlayment, the best money can buy. That product
was further overlaid with a 90# roofing paper to protect it from tile
abrasion. Then, the field tiles were installed starting at the
roof edge and working back to the ridges. All tiles were set with
copper nails, just like the original installation.
The final phase included installing the ridge and hip
tiles which include the distinctive "bump" tiles. Those tiles
proved to be the project stopper. Since only Ludowici makes them
at an exorbitant price, we attempted to get used replacements from historical tile suppliers.
Unfortunately, the
particular tiles we needed were unavailable so custom made tiles have
been ordered. Long story short...the project was stopped at 95%
complete in Fall 2001 to be resumed in Summer 2002 when the special
tiles are available. Also yet to be completed: The fascia will be
wrapped in copper, copper gutters installed and copper chimney caps
added.
-
Painting All fascia and soffit repainted. .
-
Music Room
Brothers
Joe Ford '72, John Rimel '79 and Bob Rowe '80
collaborated in this project. Due to a steam pipe leak several
years ago, the west wall was damaged along with the wall paper.
After wall and plumbing repairs were completed, Joe selected a new paper
and arranged installation. John had the piano
totally refinished (looks new) and Bob had selected memorabilia (Active
and Alumni Chapter Charters, picture of Prof Scheuch) elegantly framed
and mounted. The overall look is smashing!
-
Pocket Door Repairs
John Rimel '79 arranged repair of the long broken pocket doors to the
Music, Living and Dining Rooms.
-
New Main Floor Furniture Just in time for
Homecoming, the Reception Room, Living Room and Library were graced with
new leather furniture, end tables and lamps.
-
DSL/Broadband Wiring
Computer guru Joe Ford supplied and installed DSL/Broadband wiring
throughout the House so the brothers could take advantage of the latest
technology.
-
Sundeck Repair
A new
heavy duty waterproofing membrane was installed.
2002
-
Roof replacement project
90% complete
-
Fire Escape Upgrade. 50%
complete
-
Replace 45 windows with double pane energy efficient
units. Completed.
-
Repair the brick wall
Completed.
-
New kitchen flooring
Completed.
-
New door from Breakfast Nook to Basement
and refinish stairs. Completed
2003
2004
2005
-
Lawn sprinkler system
-
Landscape overhaul
-
Tree removals
-
Fire safety upgrades
(Siberia egress window,
-
Active Chapter Room floor
and benches refinished (by Actives)
2006
-
Carpeted Active Stairs, 2nd floor bedrooms, hallway, Siberia stairs
-
Painted 1st, 2nd and 3rd floors.
-
Draperies in Music Room, Living Room and Dining Room
-
Fire sprinkler system
-
Rubber tread system for Sundeck
Please Contribute
We need you to contribute
financially so this work can be completed. Please join the List
of Contributors by filling out a Contribution
Form. If you have a
special gift in mind, real estate or appreciated securities, please
review our Gift Acceptance Policy.
|